Morocco to tender for floating LNG terminal
RABAT (Reuters)—Morocco plans to launch a tender this summer to build a floating liquefied natural gas (LNG) terminal in the northeastern Nador West Med port, the energy ministry's head of oil and gas said on Friday.
The ministry expects to reach financial close in 2025 with construction, commissioning and commercial operations due in 2026, Abdelghafour El Hadjaoui said in a presentation seen by Reuters.
The LNG terminal will be connected to an existing pipeline that helps Morocco import 0.5 Bm3y of LNG from Spanish terminals, enough to power two small electricity production plants.
Morocco also plans to connect the same pipeline to developing gas fields in its east and west. Morocco's natural gas needs are expected to increase to 8 Bm3y in 2027 from 1 Bm3y currently, according to ministry estimates.
Nador West Med is a deepwater port under construction with expected capacity of 3.5 MM containers.
(Reporting by Ahmed EljechtimiEditing by David Goodman and Mark Potter)
Related News
Related News
- Mitsubishi Heavy Industries Compressor acquires Swiss rotating equipment maintenance company AST Turbo AG
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- Qatar’s Ras Laffan LNG hub hit by missile attack, ‘extensive damage’ reported
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- Iran attacks wipe out 17% of Qatar’s LNG capacity for up to five years

Comments