McDermott, Chiyoda and Zachry Group first liquid from Freeport LNG Train 2
McDermott International, Inc. with its partners, Chiyoda International Corporation and Zachry Group, today announced that Train 2 of the Freeport LNG project on Quintana Island in Freeport, Texas, has begun producing liquefied natural gas (LNG). This significant project achievement is a precursor to first cargo.
"First liquid for Train 2 is another great accomplishment for the Freeport LNG project," said Mark Coscio, McDermott's Senior Vice President for North, Central and South America. "As we progress to first cargo for Train 2, we applaud the diligence and commitment of the project team for driving Freeport LNG toward a safe completion."
Zachry Group, as the joint venture lead, partnered with McDermott for the Pre-FEED in 2011, followed by FEED works to support the early development stage of the project as a one-stop shop solution provider for Trains 1 and 2. Later Chiyoda joined the joint venture partnership for work related to Train 3. The project scope includes three pre-treatment trains, a liquefaction facility with three trains, a second loading berth and a 165,000 m3 full containment LNG storage tank.
Freeport LNG Trains 2 and 3 remain on schedule with Train 3 initial production of LNG scheduled for Q1 of 2020.
- Mitsubishi Heavy Industries Compressor acquires Swiss rotating equipment maintenance company AST Turbo AG
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- Qatar’s Ras Laffan LNG hub hit by missile attack, ‘extensive damage’ reported
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- Iran attacks wipe out 17% of Qatar’s LNG capacity for up to five years

Comments