Teekay says LNG tankers for Yamal project to be delivered early
Teekay LNG says four Arctic ARC7 class liquefied natural gas tankers will be delivered three to five months earlier than scheduled next year for the northern Russian Yamal project.
Two tankers, Georgiy Ushakov and Yakov Gakkel, will be delivered on Oct. 11 and Nov. 25, 2019 from earlier delivery of January and February 2020.
Two other tankers, Nikolay Yevgenov and Vladimir Voronin, to arrive June 4 and Aug. 9 2019, instead of October and November 2019.
The Yamal LNG production plant, operated by independent Russian gas producer Novatek, has been ramping up production much faster than expected.
Industry watchers say production from its two online and one commissioning plants, called trains, has been constrained by the number of ice-breaker tankers available to carry away the gas.
Arc7 carriers have the ability to use the Northern Sea Route during the summer from Russia to Asia. During winter they must go westwards to Europe.
- Mitsubishi Heavy Industries Compressor acquires Swiss rotating equipment maintenance company AST Turbo AG
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- Qatar’s Ras Laffan LNG hub hit by missile attack, ‘extensive damage’ reported
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- Iran attacks wipe out 17% of Qatar’s LNG capacity for up to five years

Comments