Teekay says LNG tankers for Yamal project to be delivered early
Teekay LNG says four Arctic ARC7 class liquefied natural gas tankers will be delivered three to five months earlier than scheduled next year for the northern Russian Yamal project.
Two tankers, Georgiy Ushakov and Yakov Gakkel, will be delivered on Oct. 11 and Nov. 25, 2019 from earlier delivery of January and February 2020.
Two other tankers, Nikolay Yevgenov and Vladimir Voronin, to arrive June 4 and Aug. 9 2019, instead of October and November 2019.
The Yamal LNG production plant, operated by independent Russian gas producer Novatek, has been ramping up production much faster than expected.
Industry watchers say production from its two online and one commissioning plants, called trains, has been constrained by the number of ice-breaker tankers available to carry away the gas.
Arc7 carriers have the ability to use the Northern Sea Route during the summer from Russia to Asia. During winter they must go westwards to Europe.

- Biogas in France: TotalEnergies starts its 2nd largest unit in Normandy
- ONEOK announces joint ventures with MPLX to build LPG export terminal at U.S. Gulf Coast location
- Ukraine plans to import 800 MMm3 of gas until April after Russian strikes
- Parker Hannifin joins iHAPC project to test H2 and argon for cleaner and more energy-efficient engine technologies
- India's BPCL signs LPG supply deal with Norway's Equinor
Comments