bp tells regulators Venture Global does not need more time to start production
Oil and gas producer bp told federal regulators on Wednesday that it has reviewed confidential commissioning documents and does not believe Venture Global LNG needs more time to begin commercial production.
Venture Global LNG's Calcasieu Pass plant has been at the center of a long-running dispute involving energy companies including bp and Shell over access to liquefied natural gas (LNG) from the plant.
Venture Global is expected to become the second largest U.S. exporter of the super chilled gas when it starts producing from its new 20-metric MMtpy facility by the end of the year. This would be its second LNG plant and will reinforce the U.S. position as the world’s largest LNG exporter.
bp said it has reviewed the documents submitted by Venture Global under a protective order and "reiterates its position that no extension is required," the company told federal regulators.
The documents cover ongoing repairs to a heat recovery steam generator that were filed under seal as well as over 124 weekly commissioning and site inspection reports.
The Arlington, Virginia-based firm's Calcasieu Pass plant has been producing and shipping LNG for more than two years, but has not provided contract customers with supplies, saying the plant is not yet fully operational.
Venture Global applied to the Federal Energy Regulatory Commission for an extension to start commercial operations of its Calcasieu Pass LNG-export facility in Louisiana to next year, but its customers said they could not justify the extension unless they had access to confidential commercial documents.
On July 25, an administrative law judge issued an order allowing bp and other Venture Global customers access to the documents.
Related News
Related News

- U.S. ethane exports to China hit new roadblock with license requirement
- Glencore to offtake 2 MMtpy of LNG from Commonwealth LNG's export facility in Cameron Parish, Louisiana
- Australia clears Woodside to run North West Shelf LNG plant to 2070
- Egypt agrees to buy up to 160 LNG cargoes through 2026
- Shell to add up to 12 MMt of additional LNG capacity by 2030
Comments