Texas tanker bottleneck grows on slow Freeport LNG restart after Beryl
The number of liquefied natural gas (LNG) tankers waiting to load at Freeport LNG in Texas has increased since the U.S. second largest exporter of the supercooled gas halted processing ahead of Hurricane Beryl’s landfall last week, according to shipping data on Thursday.
Beryl made landfall on July 8 near Matagorda, on the Texas coast, lashing the state with 80-mph (130-kph) winds that caused infrastructure damages and left more than 2 MM customers without electricity for days.
Ports and energy companies in many coastal cities, including Freeport, suffered wind damage and slow restoration of power.
Freeport LNG, which shut its three liquefaction trains on July 7 and reported wind damage after, has had a slow operational restart since.
The LNG exporter said on Monday it planned to restart one processing train this week and the remaining two trains shortly after, but production would be reduced while it continued repairs.
U.S. gas futures had dropped about 7% on Monday to a 10-week low after it became clear to the market that Freeport LNG would likely continue to operate at less than full capacity for several more days.
On Thursday, feedgas to the facility was rising with it expected to use 500 MMft3, up from 400 MMft3 on Wednesday, according to LSEG data. The gas utilization increase is seen as an indicator of LNG production starting in the first train, which can use up to 700 MMft3d.
However, vessel loading has not resumed. A total of six empty LNG tankers were anchored near the port, compared with a couple ships before the storm, with some of them accumulating more than 10 days of wait. Last-loaded vessels before Beryl's landfall departed Freeport on July 5, according to LSEG.
As of Thursday, Freeport LNG had not distributed any instruction to bring tankers into its berths, even though there were some vessels in schedule, a source familiar with the company's operations said.
The Port of Freeport last week reopened the navigation channel, but draft restrictions for vessels remain, the Brazos Pilots Association said. Long waits for vessels that have back-to-back contracts tend to lead to cargo cancellations.
Freeport LNG has canceled at least 10 cargoes for loading through August, Bloomberg reported, citing traders familiar with the matter.
Freeport LNG said on Thursday it would not comment on its commercial activity, including cargoes.
Gas flows to the seven big U.S. LNG export plants have fallen to 11.6 Bft3d so far in July due mostly to the Freeport outage, down from 12.8 Bft3d in June and a monthly record high of 14.7 Bft3d in December 2023.
Related News
Related News
- Gasum selects Wärtsilä for another bio-LNG project in Sweden
- Vanguard Renewables breaks ground on its first organics-to-renewable gas facility
- Linde selected to supply carbon capture technology to ADNOC’S Hail and Ghasha project
- Tecnimont to build waste-to-biogas plant to fuel local kitchens in India
- Topsoe, Aramco sign JDA to advance low-carbon hydrogen solutions using eREACT™
Comments