Work delays behind Troll gas field maintenance extension, Equinor says
(Reuters) - A planned maintenance outage at Norway's Troll field, Western Europe's largest, has been extended as scheduled work is taken longer than expected, operator Equinor said on Tuesday.
"The reason for the extended maintenance period at Troll A is that modification projects have taken longer than planned," said a company spokesperson.
Troll A is the platform used to produce gas from the Troll field.
The spokesperson did not provide further details on when the work would be completed.
Annual maintenance at the platform cut all of Troll's 125 mcm per day output from Aug. 26.
The maintenance was initially scheduled to end on Sept. 7 but has been extended several times. Production is currently expected to be ramped up on Sept. 14.
Troll is one of several Norwegian gas infrastructure maintenance outages currently taking place, cutting the Nordic country's gas flows to their lowest in a decade, according to LSEG analysis.
Norway's vast pipeline system typically exports at around 300 mcm per day or higher, with flows currently standing at just 137 mcm per day.
Related News
- Emerson introduces hybrid continuous gas analyzer for improved regulatory compliance and emissions control
- INNIO secures additional major order from VoltaGrid, including 300 Jenbacher gas engines
- GTT receives order from Samsung Heavy Industries for the tank design of two new very large ethane carriers
Related News
- Freeport LNG export plant in Texas reports shutdown of liquefaction train
- TotalEnergies and Mozambique announce the full restart of the $20-B Mozambique LNG project
- RWE strengthens partnerships with ADNOC and Masdar to enhance energy security in Germany and Europe
- Five energy market trends to track in 2026, the year of the glut
- Venture Global wins LNG arbitration case brought by Spain's Repsol

Comments