Gazprom completes feasibility study for Soyuz Vostok gas pipeline project
A working meeting between Alexey Miller, Chairman of the Gazprom Management Committee, and Sainbuyan Amarsaikhan, Deputy Prime Minister of Mongolia, took place today via a video link.
The parties signed a statement on the results of the consideration of the feasibility study for the Soyuz Vostok gas trunkline construction project.
As per the feasibility study, the pipeline will stretch for 962.9 kilometers in Mongolian territory, the pipes will be 1,400 millimeters in diameter, and five compressor stations will be installed. The scope of works performed as part of the feasibility study, which includes the calculation of investment and operating costs, is extensive enough for the study to serve as FEED documents.
Alexey Miller thanked Sainbuyan Amarsaikhan for the assistance provided by Mongolia. For instance, Mongolian companies performed the required on-site surveys, engineering & environmental mapping, and route analysis for the Soyuz Vostok project. The data obtained were used in the development of the gas pipeline route.
- McDermott awarded Rovuma LNG Phase 1 FEED contract in Mozambique
- Wood leads industry project to accelerate CCUS with guidelines for CO2 specifications
- ExxonMobil selects Chart Industries’ IPSMR® liquefaction technology for Mozambique LNG project
- Gasum selects Wärtsilä for another bio-LNG project in Sweden
- Vaisala seeks to remove greenwashing from carbon capture with new measurement solution
Comments