Russia's Sakhalin Energy says maintenance continues at LNG train 2
Russian LNG producer Sakhalin Energy said on Wednesday post-shutdown commissioning was continuing at the second LNG train at its Prigorodnoye production complex.
Comprehensive maintenance work, which began on July 9, had been initially due to last around 37 days, meaning the stoppages had been expected to finish by around this week. Sakhalin Energy said the first LNG train had restarted and the Amur River LNG carrier had departed with a first LNG cargo.
It was not immediately clear when the second LNG train would be back online fully, but two Singapore-based traders said that up to five LNG cargoes had been delayed from the plant.
The 11.49 million tonnes per annum (mtpa) Sakhalin-2 LNG project comprises two LNG production trains and supplies the super-chilled fuel mainly to Japan, South Korea and China.
Sakhalin Energy said the maintenance took place at several assets, including the Lunskoye-A offshore gas production platform, the onshore processing facility and the Prigorodnoye production complex.
The company added that it decided to complete some of the maintenance work which had originally been planned for autumn and winter of this year and for next year and hence, would skip a major maintenance next year.
Going forward, each train would be shut down once every two years, the company said. (Reporting by Alexander Marrow in Moscow and Jessica Jaganathan in Singapore; Editing by Jacqueline Wong)
- Gasum powers Equinor's platform supply vessel with bio-LNG
- Oman plans third LNG train, boosting domestic production to more than 15 MMtpy
- ADNOC deploys pioneering AI-enabled process optimization technology
- Mexico Pacific announces long-term LNG SPA with POSCO International
- ONEOK to acquire Medallion and controlling interest in EnLink for $5.9 B
Comments