Cheniere expects Sabine 6 LNG unit in service by 2022
U.S. LNG company Cheniere Energy Inc said the sixth train at its Sabine Pass export plant in Louisiana was about 89.6% complete and was still expected to enter commercial service in the first half of 2022.
Energy analysts said they expect the unit to start producing first LNG in test mode later this year.
Cheniere, the biggest buyer of natural gas in the United States, said it also continues to develop the Stage 3 expansion at its Corpus Christi LNG export plant in Texas.
"We expect to commence construction of the Corpus Christi Stage 3 project upon, among other things, entering into an engineering, procurement, and construction contract and additional commercial agreements, and obtaining adequate financing," the company said as part of its second quarter earnings release.
The company also reported distributable cash flow of approximately $340 million and $1.09 billion for the second quarter and first six months of 2021, respectively, an increase of approximately 30% over the first half of 2020.
It posted a net loss of $329 million for the second quarter.
The company said it was increasing full year 2021 consolidated adjusted EBITDA guidance to $4.6-$4.9 billion and full year 2021 distributable cash flow guidance to $1.8-$2.1 billion due primarily to improved LNG market margins and an increase in forecasted LNG production.
The Corpus Stage 3 expansion is designed to produce over 10 MTPA of LNG.
- ADNOC Gas awards $2.1 B in contracts to enhance LNG supply infrastructure
- U.S. Department of the Treasury releases final rules for clean hydrogen production tax credit
- Tecnimont to build waste-to-biogas plant to fuel local kitchens in India
- Indonesia regulator confirms disruption at bp's Tangguh LNG project
- Topsoe, Aramco sign JDA to advance low-carbon hydrogen solutions using eREACT™
Comments