Mammoet-Haisla J.V. successfully reaches next milestone at LNG Canada
Mammoet-Haisla Joint Venture has completed the pile handing scope for the LNG Canada project through JGC-Fluor Joint Venture in Kitimat, British Columbia, Canada. This project will export Canadian liquefied gas and put Canada on the global map of LNG exporting countries.
Mammoet-Haisla J.V. provided offloading services for incoming pipe piles throughout the pandemic, completing the scope in March. Over the course of a year, teams offloaded, transported, and placed 6,513 piles. This required 16 mobilizations and demobilizations, 39,078 chains to secure the piles, and over 50,000 working hours on site.
In addition to adjusting and adhering to constantly-changing coronavirus safety protocol and local restrictions, teams were also faced with adverse weather conditions. Being on the coast of Western Canada throughout the winter season, personnel saw upwards of 518 days of precipitation during this scope alone.
Under the agreement, the Mammoet-Haisla J.V. scope includes receiving all oversize equipment and modules at the project’s Materials Offloading Facility (MOF), transporting them to the build site, and lifting them onto final foundations. Over the span of three years, Mammoet-Haisla JV will be responsible for the horizontal and vertical movement of more than 350,000t of equipment, the largest items weighing greater than 10,000t each.
Mammoet has begun mobilization of Self-Propelled Modular Transporters (SPMT) for the upcoming work. Crews will handle onsite transport from the ships to the final installation sites. In total, there will be 88 axle-lines of SPMT’s mobilized to address this first delivery of cargo.
Mammoet-Haisla Joint Venture is pleased to announce it has completed the pile handing scope for the LNG Canada project through JGC-Fluor Joint Venture in Kitimat, British Columbia, Canada. This project will export Canadian liquefied gas and put Canada on the global map of LNG exporting countries.
Mammoet-Haisla J.V. provided offloading services for incoming pipe piles throughout the pandemic, completing the scope in March. Over the course of a year, teams offloaded, transported, and placed 6,513 piles. This required 16 mobilizations and demobilizations, 39,078 chains to secure the piles, and over 50,000 working hours on site.
In addition to adjusting and adhering to constantly-changing coronavirus safety protocol and local restrictions, teams were also faced with adverse weather conditions. Being on the coast of Western Canada throughout the winter season, personnel saw upwards of 518 days of precipitation during this scope alone.
Under the agreement, the Mammoet-Haisla J.V. scope includes receiving all oversize equipment and modules at the project’s Materials Offloading Facility (MOF), transporting them to the build site, and lifting them onto final foundations. Over the span of three years, Mammoet-Haisla JV will be responsible for the horizontal and vertical movement of more than 350,000t of equipment, the largest items weighing greater than 10,000t each.
Mammoet has begun mobilization of Self-Propelled Modular Transporters (SPMT) for the upcoming work. Crews will handle onsite transport from the ships to the final installation sites. In total, there will be 88 axle-lines of SPMT’s mobilized to address this first delivery of cargo.
- McDermott awarded Rovuma LNG Phase 1 FEED contract in Mozambique
- Wood leads industry project to accelerate CCUS with guidelines for CO2 specifications
- ExxonMobil selects Chart Industries’ IPSMR® liquefaction technology for Mozambique LNG project
- Gasum selects Wärtsilä for another bio-LNG project in Sweden
- Vaisala seeks to remove greenwashing from carbon capture with new measurement solution
Comments