Chevron expects to restart Australia's Gorgon Train 3 in coming weeks
Chevron plans to restart Train 3 at the Gorgon LNG plant off Western Australia in the "coming weeks", after it was shut for maintenance and weld inspections, a company spokesman said.
"The Gorgon Train 3 turnaround continues to safely progress with LNG train restart activities expected in the coming weeks," he said, adding that the firm is continuing to deliver natural gas to its customers.
Train 3 at the Gorgon plant has been shut since late April, with weld inspections needed after problems were discovered in propane kettles in Trains 1 and 2 at the three-train, 15.6 million tonne per year plant, which accounts for nearly 5% of global LNG trade.
Repairs have been completed on the heat exchangers in Train 1 and Train 2, Chevron had said earlier this year.
It is planning to shut more than one production train at the facility from Sept. 2 to Oct. 7 and is also planning to shut more than one and a half of an LNG train from April 4 to May 9, next year, the notice said.
(Reporting by Jessica Jaganathan; editing by Jason Neely)
- ADNOC Gas awards $2.1 B in contracts to enhance LNG supply infrastructure
- U.S. Department of the Treasury releases final rules for clean hydrogen production tax credit
- Tecnimont to build waste-to-biogas plant to fuel local kitchens in India
- Indonesia regulator confirms disruption at bp's Tangguh LNG project
- Topsoe, Aramco sign JDA to advance low-carbon hydrogen solutions using eREACT™
Comments