Nord Stream 2: Russia to Germany gas pipeline's difficult birth (2)
Reuters - The Russia-led Nord Stream 2 consortium is expected to start laying gas pipes in Danish waters from January 15, after construction was suspended for a year because of the threat of U.S. sanctions.
Led by Russia's Gazprom with Western partners, the pipeline, which would double the capacity of the existing Nord Stream 1 link, is more than 90% completed and scheduled to operate from early 2021.
The project has split the European Union, with some members saying it will undermine traditional gas transit state Ukraine and increase energy reliance on Russia.
The U.S., keen to increase LNG sales to Europe, also opposes the pipeline and has targeted some companies involved with sanctions.
Here are some key dates in Nord Stream 2's development:
2011
November: Nord Stream 2's forerunner, Nord Stream 1, a consortium mainly led by Gazprom, starts deliveries through a twin pipeline system to Europe under the Baltic Sea. The system's 55 Bm capacity is equivalent to enough gas to heat 26 million households.
Gazprom and Western partners start looking into expanding the system with another two pipelines to add a further 55 bcm³ of capacity. The project is estimated to cost $11.3 B.
2016
March: Eight EU governments - the Czech Republic, Estonia, Hungary, Latvia, Lithuania, Poland, Slovakia and Romania - object to the project, warning it could have “potentially destabilizing geopolitical consequences."
2017
April: Nord Stream 2 AG signs financing agreements with ENGIE, OMV, Shell, E.ON offshoot Uniper, and BASF's subsidiary Wintershall.
2018
January: Germany grants Nord Stream 2 a permit for construction and operation in German waters and landfall areas near Lubmin in Mecklenburg-Vorpommern.
September: Pipe-laying operations start in the Baltic Sea.
2019
January - The U.S. ambassador to Germany warns companies involved in the construction that they could face sanctions if they stick with the project. [https://bit.ly/2FhqaN3 ]
December - Swiss-Dutch company Allseas suspends its pipe-laying activities in anticipation of U.S. President Donald Trump signing a defence policy bill which includes sanctions on firms laying pipes for Nord Stream 2.
December: Trump signs the bill.
2020
January: Russian President Vladimir Putin says he hopes Nord Stream 2 will be finished by the end of the first quarter of 2021. German Chancellor Angela Merkel says she believes the project is legitimized by European regulation and therefore should be completed.
May: Germany's energy regulator declines to grant a waiver of EU gas directives to the operators of the Nord Stream 2 pipeline that require separate operators for the production, transport and distribution of energy on German territory.
May: An EU court throws out a challenge to EU gas rules from the operators of the Nord Stream 1 and Nord Stream 2 pipelines, saying it was up to individual members states to enforce them.
June: Poland starts proceedings against Gazprom, alleging the company has not cooperated with the country's anti-monopoly proceedings regarding Nord Stream 2. [nW8N28600O
August: Poland fines Gazprom $57 MM for a lack of cooperation in the matter.
Sept. 3: Pressure mounts on Merkel to reconsider the pipeline, after she says Navalny was poisoned with a Soviet-style nerve agent.
Sept. 7: Merkel's spokesman tells German newspaper Bild am Sonntag she has questioned the project.
Sept. 11: The premier of the German state of Mecklenburg-Vorpommern, where Nord Stream 2 would come ashore, says the pipeline should not be used to punish Moscow over the Navalny case. Merkel wants to agree a response with EU partners.
Sept. 15: Data shows a Russian ship sailed for the Nord Stream 2 project's supply base in Germany.
Sept. 23: The world's largest group of shipping insurers says it will not insure vessels involved in the Nord Stream 2 and TurkStream gas pipeline projects because of the threat of U.S. sanctions.
Oct. 1: Denmark gives the Nord Stream 2 consortium permission to operate in Danish waters.
Oct. 7: Poland fines Gazprom more than $7.6 B for building Nord Stream without Warsaw's approval.
Nov. 4: Gazprom files an appeal in a Polish court against that fine.
Nov. 28: Nord Stream 2 says it plans to resume pipe-laying work on a 2.6 km stretch of the pipeline before the end of the year.
Dec. 1: The maritime authority in the German city of Stralsund informs shippers about pipeline-laying activities from Dec. 5 through Dec. 31 in the Baltic sea.
Dec. 3: U.S lawmakers unveil a new U.S defense policy bill, targeting companies and individuals providing help to the project.
Dec. 11: Nord Stream 2 says Fortuna vessel has resumed pipe-laying work and would lay a 2.6 km section of the pipeline in the German Exclusive Economic Zone.
Dec. 22: The Danish Maritime Authority issued notification of pipe-laying works for the gas pipeline from Jan. 15, according to a publication on the regulator's website.
- McDermott awarded Rovuma LNG Phase 1 FEED contract in Mozambique
- Wood leads industry project to accelerate CCUS with guidelines for CO2 specifications
- ExxonMobil selects Chart Industries’ IPSMR® liquefaction technology for Mozambique LNG project
- Gasum selects Wärtsilä for another bio-LNG project in Sweden
- Vaisala seeks to remove greenwashing from carbon capture with new measurement solution
Comments