Australia's APLNG plans plant maintenance over 2020-2021
The Australia Pacific liquefied natural gas (APLNG) plant on Curtis Island off the east coast has planned maintenance in stages over this year and next, according to a notice on the Australia Energy Market Operator (AEMO) website.
The maintenance will be held in August and September this year and in March, May, July, August and October next year, according to the notice.
The longest maintenance period will be on one Train, or production unit, over mid-July to mid-August next year.
APLNG, co-owned by ConocoPhillips, Origin Energy and China's Sinopec, is a 9 million-tonne-a-year project.
LNG producers in Queensland, Australia voluntarily submit information on production maintenance at their facilities to the AEMO. The guidance is subject
to change.
Facility Dates Capacity
APLNG (Curtis Island) Aug. 4, 2020 to Aug. 12, 2020 0.5 Train outage
APLNG (Curtis Island) Sept. 1, 2020 to Sept. 9, 2020 0.5 Train outage
APLNG (Curtis Island) March 2, 2021 to March 5, 2021 0.5 Train outage
APLNG (Curtis Island) May 23, 2021 to May 26, 2021 0.5 Train outage
APLNG (Curtis Island) July 12, 2021 to Aug. 10, 2021 1 Train outage
APLNG (Curtis Island) Oct. 5, 2021 to Oct. 12, 2021 0.5 Train outage
(Reporting by Jessica Jaganathan; Editing by Subhranshu Sahu)
- McDermott awarded Rovuma LNG Phase 1 FEED contract in Mozambique
- Wood leads industry project to accelerate CCUS with guidelines for CO2 specifications
- ExxonMobil selects Chart Industries’ IPSMR® liquefaction technology for Mozambique LNG project
- Gasum selects Wärtsilä for another bio-LNG project in Sweden
- Vaisala seeks to remove greenwashing from carbon capture with new measurement solution
Comments