Venture Global Calcasieu Pass announces successful roof raising for second LNG storage tank
Venture Global LNG, Inc. announced the successful raising of the second LNG storage tank roof at the company’s Calcasieu Pass LNG export facility in Cameron Parish, Louisiana. This major project milestone was completed nearly three months ahead of schedule and comes a mere nine months after the project’s final investment decision (FID).
The North LNG Tank, Calcasieu Pass, |
The 1.8 million pound tank dome and assembly were air raised into place on Tuesday, May 19th, less than a month after the raising of the first LNG tank roof on April 24th. Air raising allows for better and safer access as well as a faster construction schedule, as the roof can be erected concurrently with the shell. The tank dome was raised in one hour and 20 minutes using 0.25 psi of pressure. CB&I Storage Tank Solutions, a division of McDermott International, Inc., is constructing the project’s dual 200,000 m3 tanks.
ACC fans being set |
Venture Global also announced that the first modules for the export facility’s 720 MW combined cycle gas turbine power plant have now arrived at site. Key components of the gas insulated switchgear (GIS) have been successfully installed on schedule, and the site has also begun receiving and setting modules for the air cooled condenser (ACC).
- Gasum powers Equinor's platform supply vessel with bio-LNG
- Oman plans third LNG train, boosting domestic production to more than 15 MMtpy
- ADNOC deploys pioneering AI-enabled process optimization technology
- Mexico Pacific announces long-term LNG SPA with POSCO International
- ONEOK to acquire Medallion and controlling interest in EnLink for $5.9 B
Comments