Chevron plans maintenance at Gorgon LNG export plant in Australia
Chevron Corp is planning to conduct maintenance rounds at its Gorgon liquefied natural gas (LNG) project through two separate periods this year and in 2020, according to a notice on the energy company's website.
Source: EWA |
The company planned to shut more than half an LNG train at the facility from Oct. 11 to Nov. 29, and more than 1 LNG train over May 23-July 11, next year, according to the notice.
A company spokesman could not immediately be reached for comment.
The three-train Gorgon project, one of the world's largest natural gas projects, can produce 15.6 million tons of LNG annually from its three trains, according to Chevron's website.
Chevron is the Gorgon project operator, with its Australian subsidiary holding a controlling 47.3%. Exxon Mobil Corp and Royal Dutch Shell each have a 25% share, and the remainder is held by Japan's Osaka Gas, Tokyo Gas and JERA.
Expected dates Scope of train shutdown
11/10/2019 - 29/11/2019 Shutdown of more than one-half of a train,
but not greater than one LNG train
23/05/2020 - 11/07/2020 Shutdown of more than one LNG
Train, but not bigger than one-and-a-half LNG trains
- Wood leads industry project to accelerate CCUS with guidelines for CO2 specifications
- ExxonMobil selects Chart Industries’ IPSMR® liquefaction technology for Mozambique LNG project
- Gasum selects Wärtsilä for another bio-LNG project in Sweden
- Vaisala seeks to remove greenwashing from carbon capture with new measurement solution
- Vanguard Renewables breaks ground on its first organics-to-renewable gas facility
Comments