Cameron LNG begins production at Train 1 of liquefaction-export facility
SAN DIEGO, -- Sempra Energy announced that Cameron LNG has begun producing liquefied natural gas (LNG) from the first liquefaction train of the Cameron LNG export project in Hackberry, La.
"Reaching this important milestone of first LNG production is truly a credit to the team at Cameron LNG and the work they've done to reach this point," said Lisa Glatch, chief operating officer of Sempra LNG and board chair for Cameron LNG. "Cameron LNG expects to load cargoes in the coming weeks – another major step forward to bringing cleaner, affordable energy to global markets."
Cameron LNG completed all major construction activities for Train 1 of the liquefaction-export project and began the commissioning and start-up process in November 2018. Last month, the facility began receiving gas flow for testing as it reached the final stage of the commissioning process.
Phase 1 of the Cameron LNG export project includes the first three liquefaction trains that will enable the export of approximately 12 million tonnes per annum of LNG, or approximately 1.7 billion cubic feet per day.
Cameron LNG is jointly owned by affiliates of Sempra LNG, Total, Mitsui & Co., Ltd., and Japan LNG Investment, LLC, a company jointly owned by Mitsubishi Corporation and Nippon Yusen Kabushiki Kaisha (NYK). Sempra Energy indirectly owns 50.2% of Cameron LNG.
Cameron LNG Phase 1 is one of five LNG export projects Sempra Energy is developing in North America. The other projects include Cameron LNG Phase 2, previously authorized by the Federal Energy Regulatory Commission (FERC), which could include up to two additional liquefaction trains and up to two additional LNG storage tanks; Port Arthur LNG in Texas, which recently was approved by FERC; and Energía Costa Azul (ECA) LNG Phase 1 and Phase 2 in Mexico.
Development of Sempra Energy's LNG export projects is contingent upon obtaining binding customer commitments, completing the required commercial agreements, securing all necessary permits, obtaining financing, other factors, and reaching final investment decisions. In addition, the ability to successfully complete construction projects, such as the Cameron LNG export project, is subject to a number of risks and uncertainties.
Sempra Energy's mission is to be North America's premier energy infrastructure company. With 2018 reported revenues of more than $11.6 billion, the San Diego-based company is the utility holding company with the largest U.S. customer base. The Sempra Energy companies' more than 20,000 employees are focused on delivering energy with purpose to approximately 40 million consumers worldwide. Sempra Energy has been consistently recognized for its leadership in diversity and inclusion, and social responsibility, and is a member of the S&P 500 Utilities Index and the Dow Jones Utility Index.
PRNewswire
- Wood leads industry project to accelerate CCUS with guidelines for CO2 specifications
- ExxonMobil selects Chart Industries’ IPSMR® liquefaction technology for Mozambique LNG project
- Gasum selects Wärtsilä for another bio-LNG project in Sweden
- Vaisala seeks to remove greenwashing from carbon capture with new measurement solution
- Vanguard Renewables breaks ground on its first organics-to-renewable gas facility
Comments