Encana starts up second Montney plant ahead of schedule, under budget
CALGARY, Alberta — Encana successfully started up the Sunrise processing plant on Sept. 27, under budget and more than one month ahead of original schedule. Sunrise is the second of three processing plants that support Encana’s condensate-focused growth plan in the Montney.
![]() |
| Photo courtesy of Encana. |
In parallel with the Sunrise and Tower facilities ramping up, the third plant, Saturn remains ahead of schedule and is on track to start up before year-end. In addition, the Towerbirch lateral pipeline which connects all three plants to the NGTL system started up on October 1.
Encana’s midstream agreement with Veresen Midstream enables Encana, via the Cutbank Ridge Partnership, to construct and operate the Tower, Sunrise and Saturn plants, as well as any future build opportunities, on behalf of Veresen Midstream on a contracted basis. Veresen Midstream funds and owns the facilities and Encana pays to use them through a fee-for-service agreement.
- ExxonMobil halts 1-Bft3d blue hydrogen project in Texas
- Aramco and Yokogawa commission multiple autonomous control AI agents at Fadhili gas plant
- Ukraine will resume gas imports via Transbalkan route in November
- Mitsubishi to inject $260 MM into Brunei LNG project
- Freeport LNG (U.S.) on track to take in more natgas on Thursday after unit outage


Comments