Japan's Inpex sees minimal cost overrun on Ichthys LNG project
5/12/2017
TOKYO (Reuters) -- Japan's biggest oil and gas explorer Inpex Corp sees minimal cost overruns on its Ichthys LNG export plant in Australia because of a start-up delay, a senior executive said on Friday.
The cost overrun could be up to a few percent if any, and there would be no material impact to the project, Inpex's Senior Managing Executive Officer Masahiro Murayama told Reuters on the sidelines of the company's full-year earnings results.
Inpex two weeks ago delayed the Ichthys start by up to six months from its original target of the third quarter this year, citing delays in the installation of offshore production facilities.
Reporting by Osamu Tsukimori; Editing by Christian Schmollinger
Sign up to Receive Our Newsletter
- Mitsubishi Heavy Industries Compressor acquires Swiss rotating equipment maintenance company AST Turbo AG
- RWE strengthens partnerships with ADNOC and Masdar to enhance energy security in Germany and Europe
- Qatar’s Ras Laffan LNG hub hit by missile attack, ‘extensive damage’ reported
- Cook Inlet LNG advances FSRU project in Alaska (U.S.)
- The Mugardos Energy Terminal is now ready to supply bioLNG to ships and tankers

Comments