BP's Tangguh Train 2 LNG plant in Indonesia to shut for nearly 2 months
3/8/2017
JAKARTA (Reuters) -- Oil and gas giant BP will shut down its Tangguh Train 2 liquefied natural gas plant in Indonesia's West Papua province for nearly two months for maintenance, a company executive said on Wednesday.
Photo Courtesy of BP. |
The routine maintenance from early April to the third week of May has been factored into Tangguh's 2017 production plan this year, BP's Indonesia country head, Dharmawan Samsu, told Reuters.
The Tangguh Train 2 plant has an annual capacity of 3.8 MMt of LNG. The overall Tangguh project, which also includes Train 1, delivered a record of 119 LNG cargos last year.
Reporting by Wilda Asmarini; Writing by Eveline Danubrata, editing by David Evans
Sign up to Receive Our Newsletter
- ADNOC Gas awards $2.1 B in contracts to enhance LNG supply infrastructure
- U.S. Department of the Treasury releases final rules for clean hydrogen production tax credit
- Topsoe, Aramco sign JDA to advance low-carbon hydrogen solutions using eREACTâ„¢
- Nicor Gas celebrates its first renewable natural gas interconnection
- EnviTec Biogas looks to expand biogas production into the U.S.
Comments