Noble Energy sees Israeli gas flows starting in five years
By JOE CARROLL
Bloomberg
Noble Energy expects to formally approve at least one natural gas development in waters off the coast of Israel by the end of next year.
Gas would probably begin to flow from one or both of the discoveries three to four years after Noble’s board makes so-called final investment decisions, or FIDs, CEO David Stover said during a conference call with analysts and investors.
With the Israeli government establishing the regulatory framework that will govern offshore energy ventures, Noble is set to begin harvesting more than 50 trillion feet of gas it has discovered in the Tamar and Leviathan fields in the eastern Mediterranean Sea.
Tamar, where the first phase of output began in 2013, already supplies the gas used to make half of Israel’s electricity.
“We’ve been looking at kind of a time frame of about a year to bring all of this together to move to FID,” Stover said during the call. “I think when you look at actual first production, we’ve been talking three years to four years from FID, the first production. There is probably an opportunity that Tamar’s project could be probably a little bit quicker than Leviathan, but we’ll just have to see how that plays out.”
Israel Framework
Israeli Economy Minister Aryeh Deri’s comment that he’s prepared to leave the ministry was seen as removing an obstacle to finalizing a regulatory framework for developing the country’s offshore gas reserves. Prime Minister Benjamin Netanyahu said Sunday that he will take over Deri’s responsibilities at the economy ministry.
“Deri was the main obstacle to the framework,” said Noam Pincu, an analyst at Psagot Investment House in Tel Aviv. “Now the companies can proceed with the development of Leviathan and Tamar and start signing contracts.”
The company expects to benefit from the knock-on effects of the 16-month rout in energy prices; canceled drilling projects around the world have slashed demand and costs to lease and buy equipment.
As a result, Stover said Noble will rebid its Israeli projects and develop new cost estimates around the middle of 2016.
Following the resignation news, shares of Noble rose 5.9% to $37.97 in New York on Monday, representing a two-month high.

- U.S. ethane exports to China hit new roadblock with license requirement
- Australia clears Woodside to run North West Shelf LNG plant to 2070
- Egypt agrees to buy up to 160 LNG cargoes through 2026
- Shell to add up to 12 MMt of additional LNG capacity by 2030
- Woodfibre LNG sets new benchmark as world’s first net-zero LNG export facility
Comments